EICMA Pre-Show Preparation and On-Site Execution
Scheduling work before, during and after the show, and managing samples Phase Timing Main Tasks Strategy 4–6 months before the show Countries, buyers, products, regulations, budget […]
Scheduling work before, during and after the show, and managing samples
| Phase | Timing | Main Tasks |
|---|---|---|
| Strategy | 4–6 months before the show | Countries, buyers, products, regulations, budget and participation format |
| Development | 2–3 months before the show | Lists, invitations, English/Italian materials, samples |
| Execution | 2–4 weeks before the show | Logistics, badges, meetings, talking points, CRM and on-site scheduling |
| Trade Days | November 3–4 | In-depth meetings, media, agent and technical meetings |
| Public Days | November 5–8 | Brand experience, consumer feedback, content and competitor observation |
| Follow-up | 48 hours to 12 weeks after the show | Lead grading, samples, quotes, video calls and sales pipeline |
For sample shipping, confirm in advance the temporary import method, applicable temporary admission documents, commercial invoice, crate or wood packaging rules, venue receiving and on-site handling. For shipments from Taiwan, check with the Taiwan External Trade Development Council (TAITRA) and your customs broker on the applicable documents, goods conditions and re-export deadlines, rather than directly applying another country’s ATA Carnet application process. Do not put all your important samples in a single piece of checked baggage, and do not assume a regular courier can deliver directly to your booth.
The on-site team should at least separate reception, technical and record-keeping roles. Every meaningful conversation should capture the company, job title, country, product needs, quantity, timeline, regulatory questions and next step. Organize your notes the evening after the Trade Days end, so information does not get mixed up once Public Days crowds arrive.
- One-page company and product overview in English.
- Featured product list and vehicle fitment information.
- Buyer interview and lead grading sheet.
- Quoting authority, sample process and post-show owners.
- Backup internet, charging, business cards and QR codes.
Pre-Show Preparation Cannot Fall on Marketing Alone
EICMA involves market, product, regulatory, logistics, finance and sales functions, and is difficult to manage with marketing staff alone. The product team should confirm featured products and technical data, regulatory or quality staff should compile tests and declarations, sales should build lists and meetings, administrative staff should handle badges, lodging and vendors, and management should authorize in advance which terms can be discussed on site.
We recommend creating a shared timeline in which each task includes an owner, deadline, dependencies and completion criteria. For example, “English catalog complete” should not just mean translation is done, but that it has passed technical, commercial and regulatory review; “samples shipped” should include tracking numbers, a receiving contact, spares and return arrangements.
Pre-show meetings should include real rehearsals of buyer conversations. Have colleagues play distributors, brand buyers and technical staff, asking about vehicle models, MOQ, lead times, certifications, warranty and exclusive distribution. Questions that cannot be answered immediately should be added to material preparation, rather than hoping to handle them on the spot.

Courtesy of EICMA
Time Management for Trade Days
Plan your exhibition work backward from the show date and set deliverables for each phase, so that tasks do not all pile up in the final month before the show.
| Timing | Focus | Output |
|---|---|---|
| 9–12 months before the show | Market and show decisions, budget, registration, lodging area | Exhibition goals, budget cap, booth requirements |
| 6–9 months before the show | Product mix, logistics plan, compliance gap review | Exhibit list, certification/documentation gap list |
| 3–6 months before the show | Booth, graphics, catalog, website landing page | Consistent show messaging, QR landing page |
| 8–12 weeks before the show | Buyer lists, invitations, meeting scheduling | A/B/C lead list, confirmed meetings |
| 2–4 weeks before the show | Exhibit shipping, pitch rehearsal, data backup | Tracking sheet, quote template, on-site SOP |
| During the show | Record needs, next steps and decision-making authority | Every lead has a note / owner / due date |
| 24–72 hours after the show | Customized follow-up, sending materials, booking the next meeting | CRM tasks, samples/quotes/technical meetings |
| 30–90 days after the show | Continued progress, conversion tracking | qualified leads→quote→sample→order funnel |